COST TO REMOVE ASTROTURF SURFACE AND REPLACE WITH GRASS:

September 11, 1992

                                                  KISD STADIUM

REMOVE ASTROTURF SURFACE AND REPLACE WITH GRASS

22* side  x 475' Long

(160'  x  350' Field

Less 40'  x  90'  x 4 Corners

108,300 S. F.  -  14,440  S. F.  =  94,000 S. F.

                                                =  10,444 S. Y.  (Approximate Area)

Remove Turf and Base Sheet      10,444 S. Y                          @  $2.00  =  $20,888.00

Remove Asphalt  1 1/2"  +-:          783 Tons

                                                    435 C. Y. Dense                  @ $20.00  =  $ 8,700.00

Remove Base Material  6"  +-:       1741 C. Y. Dense              @ $ 6.00  =   $10,448.00

Remove Subgrade  6"       +-:        1741  C. Y.  Dense             @ $ 6.00  =   $10,446.00

                                                     SUBTOTAL                                                $50,480.00

                                                     +  20% Cont.                                               $10,096.00

                                                                                                                         $60,576.00

                                                    USE                                                              $62,500.00

Drainage for Field

700 L.F.   12" PVC                                                      @ $16.50/L.F.               $11,550.00

6 connections to Inlets                                                @ $250.00 EA.              $  1,500.00

4MH's & connection to Main                                         @  $2,000.00 /EA        $  8,000.00

17,000 L.F. Drain  (6' on center)

(2/3)   4"  PVC   11,800  L.F.                                        @ $ 5.00/L. F.               $59,000.00

(1/3)   6"  PVC     5,800 L. F                                         @  $7.50/L.F.                $43,500.00

8" Depth Gravel

2350 C. Y.                                                                    @ $12.00/C.Y.               $28,200.00

Fabric

10,444  S. Y.                                                                @  $2.00?S. Y.               $20,888.00

Sand/Top Soil/Mulch Mix

2500 C. Y.                                                                    @  $20.00/C. Y.              $50,000.00

Grass/Seed/Fertilize

10,444  S. Y.  (2.2 Ac)                                                  @$1000.00/AC.              $  2,200.00

                                                                                      SUBTOTAL                  $224,838.00

Irrigation System to be Constructed:

Basic Line & Valves 1200  L. F.                                                                            $12,000.00

Hydrants/Heads                                                                                                    $  6,000.00

                                                                                                                            $242,838.00

                                                                                     +20%  Cont.                    $ 48,567.60

                                                                                                                            $291,405.60

Credit for sale of turf      10,444 S. Y.       @$0.50/SY                                         $  (5,222.00)

                                                                                                                             $286,183.60

                                                                                            TOTAL                     $348,683.60

+  Difficulty Factor                                                                                                $  51,316.40

                                                                                            TOTAL                     $400,000.00

Engineering/Surveying/Inspection                                                                       $  60,000.00

                                             TOTAL COSTS TO REPLACE ASTROTURF SURFACE AND

                                      REPLACE WITH NEW ASTROTURF SURFACE

228' wide x 475'  long

(160'  x  350' Field)

Less 40'  x  90'   x 4 corners

108,300 S. F.   -  14,440 S. F.     = 94,000 S. F.

                                                    = 10,444  S. Y.  (Approximate Area)

Remove Turf and Base Sheet

and Replace with New Base

Sheet and Carpet                          10,444  S. Y.                   = $600,000.00

Proof Roll Asphaltic Surface

and Spot Repair Soft Areas             1,000  S. Y.   @$ 25.00/SY  = $25,000.00

Credit for sale of turf                      10,444  S. Y.   @     $ 0.50/SY = $ (5,222.00)

Engineering/Inspection                                                         =  $  30,000.00

                                                        TOTAL                          = $650,000.00